Do we need an Expansion Joint?
Did you know that the Eiffel Tower grows by nearly 6 inches during the heat of summer? Or that the deck of San Francisco’s Golden Gate Bridge can sag by as much as 10 feet on a hot day – That’s the equivalent of the height of an entire story.
While these changes may sound dramatic, they’re completely normal and carefully accounted for in the design of each structure. The reason is thermal expansion: as temperatures rise, exposed structural steel expands. Engineers anticipate this natural movement, incorporating features that allow these iconic structures to safely expand and contract with changing temperatures year after year. All buildings expand, contract, and move laterally for three main reasons: there is a change in ambient temperature or there is a wind or earthquake event. Engineers account for these forces and movements to ensure that buildings remain safe, stable, and functional throughout their service life.
The question “Do we need an expansion joint?” often gets asked during preliminary design meetings. The answer is based entirely on avoiding the consequences of not having the joint. You won’t find any mandates in the building codes about the use of separation joints, as the decision depends on numerous project-specific factors. It is up to the designers to determine whether joints are needed, where they should be located, and how they will affect the building systems. The biggest driver is building size. When building approaches 400 feet in length, we begin to seriously consider dividing the structure into separate segments. However, length alone does not dictate the need for a joint. Other factors, including plan irregularities, framing irregularities, fire separation requirements, and the interface between existing and new construction, can all influence the decision. Even the locations and orientation of shear walls and X-bracing make the difference between needing joints and not needing them. One thing is certain: if a separation joint is needed and is not provided, the building will eventually express its displeasure in some very unwelcome ways.
Where to Provide Expansion Joints
At BNI, we begin considering Expansion Joints at the following conditions:
Existing Buildings: Provide expansion joints at the interface between different building sections, such as where a new addition connects to an existing structure, to accommodate differential movement.
Changes in Material: Consider joints where different materials meet, such as concrete and steel, when their differing thermal responses may result in differential movement.
Podium and Tower Interfaces: For example, in a 40-story tower surrounded by a 7-story podium, an expansion joint may be considered at the interface between the tower and podium to accommodate their differential settlement.
Parking Structures: Consider expansion joints where an enclosed building adjoins an open parking structure. The open structure is more exposed to temperature fluctuations allowing its members to expand or contract, while the enclosed building typically experiences less variation, potentially resulting in differential thermal movement.
Large or Irregularly Shaped Buildings: Consider expansion joints in buildings with large footprints or irregular configurations, where building dimensions and geometry may lead to significant thermal movement or other structural movement concerns.
And at times, architectural constraints make it difficult to locate an Expansion Joint that aligns with the building’s interior layout or exterior elevations. In these cases, we rely on advanced structural analysis software and mathematical modeling to evaluate and account for the resulting secondary effects.

Concrete Buildings
Concrete buildings have one additional phenomenon to consider: drying shrinkage. If not properly addressed through separation joints or other design measures, drying shrinkage can lead to unintended consequences. Think of taking your jeans out of the dryer: as they dry, they may shrink enough to fit more tightly. Concrete behaves similarly as it dries, undergoing volumetric shrinkage. When this movement is restrained, it can generate internal tensile stresses that lead to cracking and other unintended effects in the structure.
Together, thermal expansion, drying shrinkage, and slab shortening, which is particularly relevant to post-tensioned concrete structures, can generate substantial internal forces that cause building elements to crack, twist, or otherwise deform in unintended ways if a separation joint is not introduced. Another solution to separation joint, when concrete buildings are over 300 feet long, is a pour strip (also called a closure strip). The key advantage of a pour strip is that it is temporary, whereas an expansion joint remains permanently in the structure.
A pour strip is typically a 3- to 4-foot-wide section of the floor slab that is intentionally left open for weeks, allowing a significant portion of the concrete’s shrinkage to occur before the gap is filled with concrete. Once the pour strip is cast, the floor slab becomes continuous.
However, pour strips introduce construction challenges that must be incorporated into the contractor’s schedule. The slab remains incomplete while the strip is open, and the slab sections immediately adjacent to the strip must remain shored until the strip is filled, unless they have been designed to cantilever from each side. These requirements can delay the installation and completion of mechanical, electrical, and plumbing (MEP) systems in the area, as well as the application of final finishes.